Politics NigeriaPolicy Checked story Published 24 October 2026 · Updated 25 Oct, 18:40 UTC

One highway, two prices: the fight over what the Lagos–Calabar road really costs per kilometre

Nigeria's coastal highway is being built — that much is not in dispute. What is in dispute is the maths. The Works Minister's figures work out near ₦7.5 billion per kilometre; his critics say the same contract works out near ₦22.5 billion. We lined up every claim, checked what could be checked, and labelled the rest honestly.

Aerial view of a coastal road (illustrative)
Photo via Unsplash

Key points

  • The highway is being built — the first section runs about 47.5 km from Lagos toward the Lekki Deep Seaport axis.
  • The full route is planned at roughly 700 km to Calabar (official documents).
  • The cost fight is arithmetic: ₦7.5bn/km averaged over the whole route, vs ₦22.5bn/km on Section One alone.
  • An earlier ₦4bn/km figure was wrong — it was a design-stage estimate. The correction stays visible on this page.

Watch: the moment itself

Direct video sits at the top of Vozia's evidence ladder — the moment itself, from its owner. Embedded from its home platform; we never download or re-host it.

Video: News Central TV · Watch on YouTube

What happened

The Lagos–Calabar coastal highway is the largest road project in Nigeria's recent history: roughly 700 km of concrete-pavement highway running through the coastal states, with bridges, drainage and lighting in the price. The first section — about 47.5 km from Ahmadu Bello Way in Lagos toward the Lekki Deep Seaport axis — is the stretch actually under construction, and reporters have driven the active corridor.

The argument is about division. The Works Minister's figure of about ₦7.5 billion per kilometre spreads the contract sums across the entire planned 700 km, including sections not yet awarded. His critics divide the Section One contract by Section One's length alone and arrive at about ₦22.5 billion per kilometre — pricing the hardest, most bridge-heavy stretch as if it were typical of the whole route. Both are arithmetic. Neither, on its own, is the whole truth.

A third figure shows why this page keeps its corrections visible. An earlier claim that the road was approved at ₦4 billion per kilometre came from a design-stage estimate for a narrower asphalt specification, not the approved concrete design. Vozia repeated it as an approved figure, checked the appropriation records, and corrected it here — the correction stays on the page rather than being deleted.

Both sides, in their own words

Both sides heard. Neither believed for free. Publishing a side's version is not endorsing it — the claim checks below are where verdicts live.

Side A · The Works Minister & the Ministry

  • The contract sum, divided by the full 700 km route, gives an average of about ₦7.5 billion per kilometre.
  • The road is a concrete-pavement highway with bridges, drainage and lighting included in the price — not a plain asphalt road.
  • Section One is being built in phases, and costs differ by terrain, especially across swamp and water crossings.

Side B · Critics & opposition figures

  • Dividing the announced Section One contract by its length gives roughly ₦22.5 billion per kilometre — three times the Minister's figure.
  • The government has not published a full bill of quantities, so the public cannot verify either number.
  • At this price, the road would rank among the most expensive per kilometre anywhere in the world.

Independently verified

The first section of the highway runs about 47.5 km, from Ahmadu Bello Way in Lagos toward the Lekki Deep Seaport axis. The full route is planned at roughly 700 km, from Lagos through the coastal states to Calabar.

Not yet verified

Section One is complete and open to traffic.
§

Claim by claim

2 verified· 2 disputed· 1 not yet verified· 1 corrected
Verified
The first section of the highway runs about 47.5 km, from Ahmadu Bello Way in Lagos toward the Lekki Deep Seaport axis.

Why this label: Confirmed in the Ministry's own project documents and by reporters who have driven the active construction corridor.

On the ladder: a claim earns Verified from primary evidence, or from two independent sources that do not copy each other.

Verified
The full route is planned at roughly 700 km, from Lagos through the coastal states to Calabar.

Why this label: The planned alignment and total length are consistent across official documents and independent coverage.

On the ladder: a claim earns Verified from primary evidence, or from two independent sources that do not copy each other.

Disputed
The road costs about ₦7.5 billion per kilometre.

Why this label: This figure is reached by spreading contract sums across the entire planned 700 km — including sections not yet awarded. It is an average, not the price of the section actually under construction.

On the ladder: credible sources conflict, so we show both workings. One side's own statement is that side's position — never proof.

Disputed
The road costs about ₦22.5 billion per kilometre.

Why this label: This figure divides the Section One contract by Section One's length only. It prices the hardest, most bridge-heavy stretch as if it were typical of the whole route. Both numbers are arithmetic; neither is the whole truth on its own.

On the ladder: credible sources conflict, so we show both workings. One side's own statement is that side's position — never proof.

False – Corrected
An earlier claim that the road was approved at ₦4 billion per kilometre.
Correction stays visible
This claim was published as true and later shown to be wrong. We correct it here, in the open — we do not delete it.

Why this label: Correction: the ₦4 billion figure came from an early design-stage estimate for a narrower asphalt specification, not the approved concrete design. We originally repeated it as an approved figure; the appropriation records do not support that, and we have corrected the record here rather than deleting it.

On the ladder: stronger evidence beat the original claim. The correction stays visible — we correct in the open, we do not delete.

Not yet verified
Section One is complete and open to traffic.

Why this label: Photos circulating online show finished stretches, but neither the Ministry nor independent reporters have confirmed a full Section One opening. We are checking and will update this page.

On the ladder: the evidence so far sits low — early, single or social sources. We publish the claim as a claim, never as fact.

What we know / what we don't know yet

What we know

  • Section One runs about 47.5 km toward the Lekki Deep Seaport axis (Ministry documents + site reporting).
  • The full planned route is roughly 700 km (official documents).
  • The ₦4bn/km figure was a design-stage estimate, not an approved cost (appropriation records).

What we don't know yet

  • The true like-for-like cost per kilometre — no full bill of quantities has been published.
  • Whether Section One is complete and open to traffic.

Why it matters

This is one of the largest public works in Nigeria's history, paid for with public money. When the two sides' per-kilometre figures differ by a factor of three, ordinary people cannot tell whether the country is getting a fair price, a bargain, or being robbed — and the government has not published the bill of quantities that would settle it. That gap is exactly where checked, labelled reporting matters.

Background

  • The 700 km coastal route from Lagos to Calabar appears in official project documents as a concrete-pavement highway with bridges, drainage and lighting.

  • Section One — about 47.5 km from Ahmadu Bello Way toward the Lekki Deep Seaport axis — is the stretch under construction, built in phases across swamp and water crossings.

  • The Works Minister's public statements put the cost at about ₦7.5 billion per kilometre, averaged across the full route.

  • Opposition figures and civil-society analyses put Section One alone at about ₦22.5 billion per kilometre.

  • Vozia checked the appropriation records and corrected the earlier ₦4 billion-per-km figure on this page — the correction stays visible.

Update history

No silent edits. Every change is written here, with its time.

  • Latest

    Added the correction on the ₦4bn-per-km claim after checking appropriation records.

  • Marked the 'Section One complete' claim Not yet verified — photos show finished stretches, no official confirmation.

  • Story published with both sides' figures and the claims we could verify from Ministry documents.